In July, 2022, one new Aluminum Alloy Rod Continuous Casting and Rolling Line has been successfully debugged and put into use in *** group, Turkey, which is one of Turkey’s largest 200 industrial enterprises,and mainly engaged in Energy transmission line towers and hardware, substation steel structures, bolts, highway guardrails, lighting and GSM poles,wire and cable, etc.
The JX2340/9.5(12,15)-255/15(13,11) Type Aluminum Alloy Rod Continuous Casting and Rolling Line was designed and manufactured by our Sichuan Jiuxun Technology Co.,Ltd including furnaces and CCR Line, and we got the CE certification for this Line as well. This line can be used for producing the Pure aluminum rod and alloy Rod for electric purpose with the dia 9.5mm, 12mm, 15mm and the capacity is 5t/h-6t/h.
The process of this line :
Aluminum ingot/scrap aluminum wire /large aluminum sheet (SOW)→25t/h melting furnace → 2 sets of 12 Tilting holding furnace → electromagnetic stirrer → degassing and filtering → tundish → 4-wheel continuous casting machine →upward hauling → automatic shearer → waste bar discharger →Casting Bar Straightening Machine→ induction heater → automatic feeding continuous rolling mill → Roller type Al Rod leading pipe (without butter oil) and new dual baskets drop coiling mechanism → Al alloy rod
In Dec, 2021, We shipped this line. In March 2022, even the COVID situation was still not optimistic at home and abroad, we kept our promise and send our 1st batch of engineers to Turkey and started for the Installation guiding. Until Beginning of July, the Natural Gas Permission was got and we got the successful commissioning by the mutual teams’ great efforts and well-cooperation.
For this project, the *** group provided an excellent team for installation and commissioning, and also arranged the Chinese Engineers very well and friendly, even established the friendship. End of July, our Chinese Engineers back to China Safety, after the quarantine period, the engineers back home and enjoy a short time together with their family, then went to the site of new client and project.
We must give our engineers thumbs up, thanks for their great efforts, thanks for their hard-working.
When you hoist the sails to cross the sea, you will ride the winds and cleave the waves.
TO BE THE BEST ONE, WE ARE ALWAYS ON THE WAY AND NEVER STOP.
Post time: Oct-25-2022